BC Hydro says halting Site C would cost taxpayers $500 million? Not building it at all will save us over $8 billion dollars.

No Strings Attached: Laila Yuile on people, politics and life in B.C.

Sometimes, one woman can only take so much. And when I saw yet another headline last night blaring: 

“BC Hydro says halting Site C would cost $500 million”

I really and truly, had enough.

“A stop-work order for the Site C dam will cause “extreme prejudice” to BC Hydro at a cost of hundreds of millions of dollars and a one-year delay in the construction schedule, the utility’s lawyer says.

Mark Andrews told a B.C. Supreme Court judge that critical milestones will not be met if an injunction is granted to a pair of First Nations.

“This injunction is going to drive a truck into the schedule of the project at this stage in particular,” Andrews said Wednesday.

The West Moberly and Prophet River First Nations are challenging the nearly $9-billion project by arguing they were not properly consulted before permits were granted for Site C, the third dam on…

View original post 1,118 more words

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s